Government To Terminate Six Abandoned Projects In Niger Delta

No comment
Wednesday, May 17th, 2017
No comment

Crude oil flows at the banks of a river, after a Shell pipeline leaked, in the Oloma community in Nigeria"s delta region. REUTERS/Tife Owolabi

The Ministry of Niger Delta Affairs has concluded arrangements to terminate about six abandoned projects spread across the region with a view to enhance the development of the region.

The Minister, Uguru Usani, made this known while receiving the report on the audit and review of the East-west road and other project of its Ministry in Abuja.

Mr. Usani said that following the report from the Ministerial Technical Audit Committee on the contracts awarded from 2009 – 2015 in the Niger Delta, some projects were proposed for termination.

He listed the projects to include construction of OkpuhutaMbano Junction – Orie market -Lomara- Igwebulka (35km) – Abia State; Land reclamation and Erosion control project at OguduAbia Phase I, Abia State.

Others are Idoro-Eastern Itam Water Supply Scheme Akwa Ibom; Construction of Mbak Atai-Ikot Ntu-MkpetiOkuiboku road project (13.86km) Akwa Ibom State; Ukparam Water Supply Scheme and Construction and Supervision of Omelema – Agada II Road, Rivers State. Project Length 14.415km.

The minister said the projects were proposed for termination as a result of lack of capacity to complete the work as witnessed on site.

Mr. Usani said the committee juxtaposed its findings from project sites against facts retrieved from available documents domiciled in the departments that supervised the projects.

According to him, there were violation of contract award process, from the cycle of procurement planning to contract award. He said the committee noticed inconsistencies with the provisions of vital aspects of the Procurement Act.

“Prominent among other issues of violation were indiscriminate award of contract by initiating and benefiting departments without the leading and guiding role of the procurement department,” he said.

“Awards never took cognizance of availability of funds and annual appropriation provisions.”

The minister said the structure and content of some contract agreements lack checks and balances, saying that they hardly protect the interest of the Ministry in case of disputes.

He said the imminent picture of abandoned and uncompleted projects was as disturbing as the retinue of projects that extremely exceeded the dates of completion.

“This manifestly, emanated from inconsistency in government annual budgetary provision and lack of capacity to deliver especially where funds released do not correspond with performance.

“Most contracts were awarded with specific dates of completion but were not captured in subsequent appropriations,” he said.